| Client: Nelsam/Mclaren Site: Battersea, London Date of Install: July – August 2022 Duration of Works: 55 days |
| |
| Client: B & K Structures Site: Peterborough Date of Install: June 2022 Duration of Works: 15 days |
| |
| Client: BAM Construction Site: Plymouth Date of Install: May 2022 Duration of Works: 8 days |
| |
| Client: X Construct Site: Milton Keynes Date of Install: March – April 2022 Duration of Works: 13 days |
| |
| Client: Copper Projects Site: Sugar House Island, London Date of Install: February – April 2022 Duration of Works: 55 days |
| |
| Client: Tilbury Douglas Site: Walsall Date of Install: January 2022 Duration of Works: 6 days |
| |
| Client: DE Group Site: London (Opposite the Ritz) Date of Install: December – February 2021/2022 Duration of Works: 95 days |
| |
| Client: BSS / Briggs Site: Birmingham Date of Install: October – Nov 2021 Duration of Works: 50 days |
| |
| Client: Level 1 Site: London, FB Building Date of Install: September 2021 Duration of Works: 8 days |
| |
| Client: Willmott Dixon Site: Birmingham Date of Install: August 2021 Duration of Works: 25 days |
| |
| Client: Galliford Try Construction Site: Bristol Date of Install: July 2021 Duration of Works: 7 days |
| |
| Client: Bowmer & Kirkland Site: Leatherhead Date of Install: June 2021 Duration of Works: 3 days |
| |
| Client: Willmott Dixon Site: Ashby-De-La-Zouch Date of Install: May 2021 Duration of Works: 5 days |
| |
| Client: Blenheim House Construction Site: Broadwick St, London Date of Install: April 2021 Duration of Works: 8 days |
| |
| Client: OD Group Site: New Malden Date of Install: March 2021 Duration of Works: 21 days |
| |
| Client: Tolent Construction Site: Hackney Date of Install: Feb 2021 Duration of Works: 5 days |
| |
| Client: Bouygues UK Site: UCLH, London Date of Install: Dec – January 2020 Duration of Works: 45 days |
| |
| Client: Balfour Beatty Site: Midland Metropolitan Hospital, Smethwick, Birmingham Date of Install: Nov 2020 commenced Duration of Works: Ongoing (as at August 2022) |
| |
| Client: Blenheim House Construction Site: Curzon St, London Date of Install: Oct 2020 Duration of Works: 6 days |
| Client: BK Structures Site: Harwell Date of Install: Sept 2020 Duration of Works: 10 days |
| |
| Client: 8 Build Site: Cannon Street, London Date of Install: Aug 2020 Duration of Works: 40 days (2 visits) |
| |
| Client: Various Site: Battersea Power Station Date of Install: July 2020 Duration of Works: 75 days |
| Client: Bowmer & Kirkland Site: Isleworth Date of Install: June 2020 Duration of Works: 5 days |
| |
| Client: Galliford Try Site: Bristol Date of Install: May/June 2020 Duration of Works: 35 days |
| Client: Structuretone Site: Dagenham Date of Install: May 2020 Duration of Works: 15 days |
| Client: J Coffey Site: Central London Date of Install: Apr 2020 Duration of Works: 10 days |
| Client: Morgan Sindall Site: Basildon Date of Install: Mar 2020 Duration of Works: 5 days |
| |
| Client: Structuretone Site: Dagenham Date of Install: Jan 2020 Duration of Works: 10 days |
| |
| Client: 8 Build Site: Central London Date of Install: Dec 2019 Duration of Works: 20 days |
| |
| Client: Bouygues Site: Central London Date of Install: Nov 2019 Duration of Works: 40 days |
| |
| Client: Wates Construction Site: Loughborough Date of Install: Oct 2019 Duration of Works: 15 days |
| |
| Client: Galliford Try Site: Birmingham Date of Install: Mar-Sept 2019 Duration of Works: 120 days |
| |
| Client: Morgan Sindall Site: Cambridge Date of Install: Aug 2019 Duration of Works: 5 days |
| |
| Client: Whitehall Homes Site: East Grinstead Date of Install: May/Jun 2019 Duration of Works: 6 days |
| |
| Client: Midas Construction Site: Paignton Date of Install: April 2019 Duration of Works: 4 days |
| |
| Client: Willmott Dixon Site: Market Harborough Date of Install: March 2019 Duration of Works: 5 days |
| |
| Client: Vinci Construction Site: Croydon Date of Install: February 2019 Duration of Works: 13 days |
| |
| Client: Wates Construction Site: London Date of Install: January 2019 Duration of Works: 17 days |
| |
| Client: Structuretone Site: London Date of Install: November/December 2018 Duration of Works: 20 days |
| |
| Client: Bouygues UK Site: London Date of Install: November/December 2018 Duration of Works: 35 days |
| |
| Client: Blenheim House Construction Site: Woking Date of Install: October 2018 Duration of Works: 18 days (2 visits) |
| |
| Client: Phoenix Site: London Date of Install: September 2018 Duration of Works: 3 days |
| |
| Client: Kier Construction Site: Cardiff Date of Install: August 2018 Duration of Works: 7 days |
| |
| Client: Morgan Sindall Site: Manchester Date of Install: July 2018 Duration of Works: 6 days |
| |
| Client: Kier Construction Site: Swansea Date of Install: June 2018 Duration of Works: 20 days |
| |
| Client: Graham Construction Site: London Date of Install: May 2018 Duration of Works: 25 days |
| |
| Client: Kier Construction Site: Cambridge Date of Install: April 2018 Duration of Works: 5 days |
| |
| Client: Kier Construction Site: Harrow Date of Install: April 2018 Duration of Works: 17 days |
| |
| Client: SOHO House Site: Soho Date of Install: April 2018 Duration of Works: 7 days |
| |
| Client: Spence Site: Waterloo Date of Install: March 2018 Duration of Works: 15 days |
| |
| Client: ESG Plc Site: Welwyn Garden City Date of Install: Jan 2018 Duration of Works: 5 days |
| |
| Client: Virtus Contracts Site: London Date of Install: Dec 2017 Duration of Works: 6 days |
| |
| Client: Carillion Construction Site: Birmingham Date of Install: Oct 2017-Jan 2018 Duration of Works: 98 days |
| |
| Client: FDL/Mclaren Construction Site: London Date of Install: Oct-Nov 2017 Duration of Works: 20 days |
| |
| Client: Bouygues UK Site: Hounslow Date of Install: Aug-Nov 2017 Duration of Works: 30 days |
| |
| Client: Phoenix ME Site: London Date of Install: July-Nov 2017 Duration of Works: 58 days |
| |
| Client: Kier Construction Site: Oxford Date of Install: June 2017 Duration of Works: 6 days |
| |
| Client: Kier Construction Site: Cambridge Date of Install: May 2017 Duration of Works: 18 days |
| |
| Client: Morgan Sindal Site: Henley Date of Install: May 2017 Duration of Works: 5 days |
| |
| Client: Kier Construction Site: Glasgow, Scotland Date of Install: April 2017 Duration of Works: 6 days |
| |
| Client: Jaguar / Land Securities Site: Central London Date of Install: Mar 2017 Duration of Works: 18 days |
| |
| Client: Bowmer & Kirkland Site: Slough Date of Install: Mar 2017 Duration of Works: 29 days |
| |
| Client: Carillion Site: Clyde, Scotland Date of Install: Feb 2017 Duration of Works: 12 days |
| |
| Client: Willmott Dixon Site: Bristol Date of Install: Jan 2017 Duration of Works: 5 days |
| |
| Client: BAM Site: Ilfracombe Date of Install: Dec 2016 Duration of Works: 5 days |
| |
| Client: Interserve Site: Hull Date of Install: Nov 2016 Duration of Works: 8 days |
| |
| Client: Bouygues UK Site: Cambridge Date of Install: Oct/Nov 2016 Duration of Works: 38 days |
| |
| Client: Mala Site: London Date of Install: Sept/Oct 2016 Duration of Works: 5 days |
| |
| Client: Kier Construction Site: Bodmin Date of Install: Sept 2016 Duration of Works: 6 days |
| |
| Client: SDC Builders Site: Science Park, Cambridge Date of Install: Sept 2016 Duration of Works: 15 days |
| |
| Client: Phoenix ME / MACE Site: Knightsbridge, London Date of Install: August 2016 Duration of Works: 3 days |
| |
| Client: Balfour Beatty Site: Edgbaston Date of Install: August 2016 Duration of Works: 5 days |
| |
| Client: Level 1 Site: London Date of Install: June 2016 Duration of Works: 5 days |
| |
| Client: J Coffey / Mace Site: London Date of Install: May – June 2016 Duration of Works: 25 days |
| |
| Client: Kier Construction Site: Slough Date of Install: May 2016 Duration of Works: 10 days |
| |
| Client: Interserve Site: Near Bury St Edmunds, Suffolk Date of Install: May 2016 Duration of Works: 7 days |
| |
| Client: SDC Builders Site: Cambridge Date of Install: April – June 2016 Duration of Works: 17 days |
| |
| Client: Kier Construction Site: London Date of Install: March 2016 Duration of Works: 5 days |
| |
| Client: Mace Group Site: London Date of Install: January 2016 Duration of Works: 6 days |
| |
| Client: Balfour Beatty Site: London Date of Install: November 2015 Duration of Works: 15 days |
| |
| Client: WF / Kier Site: Oswestry Date of Install: October 2015 Duration of Works: 5 days |
| |
| Client: Ellis Building Contractors Site: Croydon Date of Install: October 2015 Duration of Works: 2 days |
| |
| Client: TI / Carillion Site: Somerset Date of Install: September 2015 Duration of Works: 3 days |
| |
| Client: Morgan Sindall Site: Cambridge Date of Install: July 2015 Duration of Works: 5 days |